Theresa is a project manager hired to manage a construction project. The budgeted cost of the project was planned to be $120,000. The project had
Theresa is a project manager hired to manage a construction project. The budgeted cost of the project was planned to be $120,000. The project had 25 stakeholders and had several change requests. Since the beginning she has incorporated 12 approved change requests to the original scope of the project. The total cost of all the implemented changes was $15,000 and the cost spent on evaluating these change requests was $3,000. What is the revised budget for the project?