This problem related to Manufacturing Systems subject. Production is set to occur on a two - machine line with deterministic processing times and geometric repair

This problem related to Manufacturing Systems subject.
Production is set to occur on a two-machine line with deterministic processing times and geometric
repair and failure times, with operation-dependent failures. The operation time is 1 minute per
machine. The mean time to failure of each machine is 16 hours and 40 minutes.|The mean down time
is 1 hour, 51 minutes, and 7 seconds.
Part 1
Calculate the production rate of the following lines in parts per minute.
a) What is the production rate of a zero-buffer line?
b) What is the production rate of an infinite buffer line?
Answer in 4 decimal places.
Part 2
Assume the factory works 50 weeks, with 40 hours per week on average.
a) What is the smallest buffer that allows an expected production rate of 106,000 items/year.
Round to the nearest integer.
Part 3
The factory gets $1 for each item sold, and it costs $20 to hold an item in inventory.
a) What is the profit if the factory sizes the buffer to make 106,000 units?
b) What is the optimal buffer size for maximizing profit?
c) What is the optimal profit?
Round to the nearest integer.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Chuck Williams

4th Edition

978-0324316797, 0324316798

More Books

Students also viewed these General Management questions

Question

Describe a smart car.

Answered: 1 week ago