This Question is Operating Systems. Please answer it as soon as possible. Two processes, p1 and p2 arrive at time 0 and start executing using
This Question is Operating Systems. Please answer it as soon as possible.
Two processes, p1 and p2 arrive at time 0 and start executing using RR scheduling. The total CPU time of p1 is 70 time units, and p2 is 10. The quantum is Q = 10. The context switching time, which follows every Q, is S = 1. Calculate the Turnaround Time (TT) and Average Turnaround time (ATT)