This table shows the activities, three estimates of project durations, and the precedence relationships for a project. Pessimistic TIme Immediate Predecessor A 3 4 5
This table shows the activities, three estimates of project durations, and the precedence relationships for a project.
a. Construct an activity on node (AON) network for this project.
b. Calculate the expected time and standard deviation for each project activity.
c. Calculate the length of each project path and identify the expected project completion time.
d. Calculate the expected project completion time.
e. Calculate the variance associated with the project completion time.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started