Question

1 Approved Answer

Thrasher Construction Co . was contracted to construct a building for $ 9 2 5 , 0 0 0 . The building is owned by

Thrasher Construction Co. was contracted to construct a building for $925,000. The building is owned by the customer throughout the contract period. The contract provides for progress payments. Thrashers accounting year ends 31 December. Work began under the contract on 1 July 20X5, and was completed on 30 September 20X7. Construction activities are summarized below by year:
20X5 Construction costs incurred during the year, $170,500; estimated costs to complete, $596,700; progress billings during the year, $144,800; and collections, $132,600.
20X6 Construction costs incurred during the year, $426,200; estimated costs to complete, $180,000; progress billing during the year, $362,200; and collections, $360,000.
20X7 Construction costs incurred during the year, $185,000. Because the contract was completed, the remaining balance was billed and later collected in full per the contract.
Requilred:
Prepare Thrasher's journal entries to record these events. Assume that percentage of completion is measured by the ratio of costs
incurred to date divided by total estimated construction costs. (If no entry is requlred for a transactlon/event, select "No journal
entry required" In the first account fleld. Do not round Intermedlate calculatlons. Round your final answers View transaction list
1 Record the construction costs incurred.
2 Record the progress billings.
3 Record the collection of billings.
4 Record the recognition of income.
5 Record entry to recognize costs related to revenue
recognized to date.
Note : = journal entry has been entered Provide the balances that would be shown on the SCI and SFP for this contract for each year. (Do not round Intermedlate
calculations. Round your final answers to the nearest whole dollar.)
3-a. Now assume that the building is owned by Thrasher throughout the construction period and title is transferred to the customer
only once the bullding is fully constructed. Prepare the journal entries required to record the events from 205 to 207.(If no entry is
requlred for a transactlon/event, select "No Journal entry requlred" In the first account fleld.)
Journal entry worksheet
Record the construction costs incurred.
Note: Enter debits before credits.1 Record the construction costs incurred.
2 Record the progress billings.
3 Record the collection of billings.
Note : 0 journal entry has been entered
Journal entry worksheet
1
3
4
5
Record the construction costs incurred.
Note: Enter debits before credits.3-b. Calculate the balances that would be shown on the SCI and SFP for this contract for each year.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Public Sector Accounting And Budgeting For Non-Specialists

Authors: G. Jan Van Helden, Ron Hodges

1st Edition

1137376988, 9781137376985

More Books

Students also viewed these Accounting questions