three jobs are to be scheduled on two machines A and B ,assume that the jobs are processed in the sequence A-B. (A has to
three jobs are to be scheduled on two machines A and B ,assume that the jobs are processed in the sequence A-B. (A has to finish the job before B can continue the job )the processing times are
job | A | B |
1 | 5 | 4 |
2 | 7 | 7 |
3 | 3 | 5 |
draw a Gantt chart that shows the schedule corresponding to the sequence 1-2-3 of the jobs