Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table.

Three recent college graduates have formed a partnership and have opened an advertising firm.
Their first project consists of activities listed in the following table.
Activity Immediate Predecessor Time in days
A -6
B A 8
C A 8
D B 14
E C,D 6
F E 7
G E 5
H G,F 4
I H 7
What is the minimum time required to complete the project?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel Jr.

8th edition

470533021, 978-0470533024

More Books

Students also viewed these General Management questions

Question

=+ What is Pats minimax choice?

Answered: 1 week ago