Three recent college graduates have formed o partnership and have opened an advertising firm. Their first project consists of activities listed in the following table, L se Tahie A Click here for the Excel Data File a. What is the probability that the project can be completed in 24 days or less? In 21 days or less? (Round your te and z values to 2 decimal places and "Standard deviation" to 3 decimal places. Round your final answers to 4 decimal places.) b. Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5,6 , and 7 . Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21 . (Round your intermediate calculations to 3 decimal places and final answers to 4 decimal places.) b. Suppose it is now the end of the seventh day and that activities A and B hove been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5,6 , and 7 . Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21 (Round your intermediate calculations to 3 decimal places and final answers to 4 decimal places.) c. The partners have decided that shortening the project by two days would be beneficial. They have estimated the daily crashing costs for each activity in thousands, as shown in the following table. Which activities should be crashed? fx. Enter text on formula hete \begin{tabular}{|c|c|c|c|c|c|c|c|} \hline 4 & A & B & c & D & E. & i & G \\ \hline 1 & & & \multicolumn{3}{|c|}{ TIME IN DAYS } & & \\ \hline 2 & Activity & \begin{tabular}{l} Immediate \\ Predecessor \end{tabular} & Optimistic & Most Likely & Pessimistic. & & \\ \hline 3. & A & - & 5 & 6 & 7 & & \\ \hline 4 & B & - & 8 & =8 & 11 & & \\ \hline 5 & C & A & 6 & 8 & 11 & & \\ \hline 6. & D & - & 9 & 12 & 15 & & \\ \hline 7 & E & C & 5 & 6 & 9 & & \\ \hline 8 & F & D & 5 & 6 & 7 & & \\ \hline 9 & G & F & 2 & 3 & 7 & & \\ \hline 10 & H & B & 4 & 4 & 5 & & ; \\ \hline 11 & 1 & H & 5 & 7 & 8 & & \\ \hline 12 & End & E,G,1 & & & & & \\ \hline 13 & & & & & & & \\ \hline 14 & Part c: & & & & & & \\ \hline 15 & & & & & & & \\ \hline 16 & Activity & First Crash & Second Crash & & & & \\ \hline 17 & c & $8 & $10 & & & & \\ \hline 18 & D & $10 & $11 & & & & \\ \hline 19 & E & $9 & $10 & & & & \\ \hline 20 & F & $7 & $9 & & & & \\ \hline 21 & G & $8 & $9 & & & & \\ \hline 22 & H & $7 & $8 & & & & \\ \hline 23 & 1 & $6 & $8 & & & & \\ \hline 24 & & & & & & & \\ \hline \end{tabular}