Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Tilly Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and

Tilly Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below.

2012 2013
Costs Incurred During The Year $450,000 $1,100,000
Estimated Costs To Complete $1,050,000 $0
Bilings During The Year $400,000 $1,400,00
Cash Collections During The Year $300,000 $1,500,000

Assume that Tilly reports under IFRS and uses the cost recovery method for revenue recognition.

Required:

A. Compute the amount of gross profit recognized during 2012 and 2013

B. Prepare the appropriate journal entries to record revenue and gross profit during 2012 and 2013

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Local Union Financial Records A Guide For Local Union Trustees

Authors: John Lund

1st Edition

0875461948, 978-0875461946

More Books

Students also viewed these Accounting questions

Question

What steps should be taken to address any undesirable phenomena?

Answered: 1 week ago