Time left 0 : 2 6 : 1 3 Question 5 0 Not yet answered Marked out of 5 Flag question Question text * *

Time left 0:26:13
Question 50
Not yet answered
Marked out of 5
Flag question
Question text
** This question is worth 5 marks **
A project has the activity duration and cost information indicated in the table where all times are in weeks. For every week longer than 30 weeks, there is a penalty of $300. By balancing the cost of penalty against the crash costs of the activities, what is the total crashed cost for completing this project?
Activity
Normal time
Crash time
Normal Cost
Crash Cost
Predecessor
A
8
5
$1,000
2,000
B
6
4
1,500
2,000
A
C
8
5
1,800
2,300
A
D
12
9
1,000
1,800
B
E
14
11
950
1,450
B
F
9
7
1,500
1,900
C, D
G
7
5
2,300
2,800
E, F
Question 50Select one:
a.
$13,550
b.
$14,250
c.
$13,950
d.
$13,150

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: R. Dan Reid, Nada R. Sanders

4th edition

9780470556702, 470325046, 470556706, 978-0470325049

More Books

Students also viewed these General Management questions