A project has the activity duration and cost information indicated in the table where all times are in weeks. For every week longer than weeks, there is a penalty of $ By balancing the cost of penalty against the crash costs of the activities, what is the total crashed cost for completing this project?
Activity
Normal time
Crash time
Normal Cost
Crash Cost
Predecessor
A
$
B
A
C
A
D
B
E
B
F
C D
G
E F
Question Select one:
a
$
b
$
c
$
d
$
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started