Question

1 Approved Answer

Time Remaining 1 hour 1 8 minutes 1 1 seconds 0 1 : 1 8 : 1 1 eBookItem 2 Time Remaining 1 hour 1

Time Remaining 1 hour 18 minutes 11 seconds01:18:11
eBookItem 2
Time Remaining 1 hour 18 minutes 11 seconds01:18:11
A manufacturer has accepted the following jobs for July. Today is Thursday, end of June. The nonworking days in July are July 1,2,3,10,17,24,30, and 31.
Job Date Order Received Production Time Including Setup Due Date Due Date in Working Days From Now
A 6/46.25 days 11 July 7
B 6/72.5 days 8 July 5
C 6/128.25 days 25 July 19
D 6/143.5 days 19 July 14
E 6/159.5 days 29 July 23
a. Determine the processing sequence using priority rules FCFS, SPT, EDD, or CR.
Rule Sequence
FCFS
(Click to select)
SPT
(Click to select)
EDD
(Click to select)
CR
(Click to select)
b. For each rule, find the average flow time and the average days late. (Do not round intermediate calculations. Round the final answers to 2 decimal places.)
Rule Average flow time Average days late
FCFS
SPT
EDD
CR
c. Advise on which priority rule to use: FCFS, SPT, EDD, or CR.
(Click to select)
has the lowest avg. flow time;
(Click to select)
has the lowest avg. days late.
(Click to select)
rule is good to use.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Information Systems

Authors: Ken Laudon, Jane Laudon

12th Edition

0132478080, 9780132478083

More Books

Students also viewed these General Management questions