Question

1 Approved Answer

Times are in days. Assume only one critical path exists which is: A, C, E, F Activity Optimistic Most Likely Pessimistic Critical? ________________________________________________________________ A ---

Times are in days. Assume only one critical path exists which is: A, C, E, F

Activity Optimistic Most Likely Pessimistic Critical?

________________________________________________________________

A --- 4 --- 6 --- 8 --- YES

B --- 2 --- 7 --- 9 --- NO

C --- 8 --- 10 --- 18 --- YES

D --- 14 --- 16 --- 19 --- NO

E --- 6 --- 8 --- 10 --- YES

F --- 2 --- 4 --- 12 --- YES

What is the expected project completion time? Round off to the nearest integer.

What is the standard deviation of project completion time?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Algebra 2

Authors: Randall I. Charles, Basia Hall, Dan Kennedy, Laurie E Bass

Student Edition

0133500438, 978-0133500431

More Books

Students also viewed these Mathematics questions