Tip: To address the stipulation that that at least two of the projects 1, 3, 5, 6 must be undertaken , make Sum of B12,

image text in transcribed

Tip: To address the stipulation that that at least two of the projects 1, 3, 5, 6 must be undertaken , make Sum of B12, D12, F12,G12 >= 2

To address the stipulation that Project 4 cannot be undertaken unless both projects 1 & 3 are also undertaken make E12

sold on the open market? 4. Real Estate Project Selection. Brooks Development Corporation (BDC) faces the following capital budgeting decision. Six real estate projects are available for investment. The net present value and expenditures required for each project (in millions of dollars) are as follows: There are conditions that limit the investment alternatives: - At least two of projects 1,3,5, and 6 must be undertaken. - If either project 3 or 5 is undertaken, they must both be undertaken. - Project 4 cannot be undertaken unless both projects 1 and 3 also are undertaken. The budget for this investment period is $220 million. a. Formulate a binary integer program that will enable BDC to find the projects to invest in to maximize net present value, while satisfying all project restrictions and not exceeding the budget. b. Solve the model formulated in part (a). What is the optimal net present value? Which projects will be undertaken? How much of the budget is unused? sold on the open market? 4. Real Estate Project Selection. Brooks Development Corporation (BDC) faces the following capital budgeting decision. Six real estate projects are available for investment. The net present value and expenditures required for each project (in millions of dollars) are as follows: There are conditions that limit the investment alternatives: - At least two of projects 1,3,5, and 6 must be undertaken. - If either project 3 or 5 is undertaken, they must both be undertaken. - Project 4 cannot be undertaken unless both projects 1 and 3 also are undertaken. The budget for this investment period is $220 million. a. Formulate a binary integer program that will enable BDC to find the projects to invest in to maximize net present value, while satisfying all project restrictions and not exceeding the budget. b. Solve the model formulated in part (a). What is the optimal net present value? Which projects will be undertaken? How much of the budget is unused

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

explain what is meant by the terms unitarism and pluralism

Answered: 1 week ago