Today (year 0) a new 7-megaWatt (MW) solar panel farm is constructed at a cost of MYR14 million. 4 years from today, a smaller 6-MW
Today (year 0) a new 7-megaWatt (MW) solar panel farm is constructed at a cost of MYR14 million. 4 years from today, a smaller 6-MW solar farm will be added to the existing farm. The inflation rate on solar panel construction projects averages 8% per year. If the cost-capacity factor is 0.85 for solar panel construction, what is the estimated capital investment for the smaller 6-MW solar farm?