Question
Toefield Inc. has developed a powerful efficient snow remover that is significantly less polluting than existing snow removers currently on the market. The company spent
Toefield Inc. has developed a powerful efficient snow remover that is significantly less polluting than existing snow removers currently on the market. The company spent $2,000,000 developing this product and the marketing department spent another $300,000 to assess the market demand. It would cost $20 million at Year 0 to buy the equipment necessary to manufacture the efficient snow blower. The project would require net working capital at the beginning of each year equal to 20% of sales (NOWC0 = 20%(Sales1), NOWC1 = 20%(Sales2), etc.). The efficient snow blowers would sell for $3,000 per unit, and Toefield believes that variable costs would amount to $790 per unit. The company expects that the sales price and variable costs would increase at the inflation rate of 2% after year 1. The company’s non-variable costs would be $800,000 in Year 1 and are expected to increase with inflation. The efficient snow blower project would have a life of 4 years. If the project is undertaken, it must be continued for the entire 4 years. Also, the project’s returns are expected to be highly correlated with returns on the firm’s other assets. The firm believes it could sell 5,000 units per year.
The equipment would be depreciated using a CCA rate of 30%. The estimated market value of the equipment at the end of the project’s 4-year life is $500,000. Toefield has other assets in this asset class. Toefield Inc.’s federal-plus-provincial tax rate is 30%. Its cost of capital is 9% for average risk projects. Low-risk projects are evaluated with a WACC of 6%, and high-risk projects at 12%.
a. Develop a spreadsheet model and use it to find the project’s NPV, IRR, and payback.
b. Conduct a sensitivity analysis to determine the sensitivity of NPV to changes in the sales price, variable costs per unit, and number of units sold. Set these variables’ values at 10% and 25% above and below their base case values. Include a graph in your analysis.
c. Would you recommend that the project be accepted? Explain.
Step by Step Solution
3.48 Rating (148 Votes )
There are 3 Steps involved in it
Step: 1
a Develop a spreadsheet model and use it to find the projects NPV IRR and payback Part 1 Input Data ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started