Question

1 Approved Answer

Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to

Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory.

In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four months:

Month
1 2 3 4
Quality control measures:
Number of defects 191 169 130 91
Number of warranty claims 52 45 36 33
Number of customer complaints 108 102 85 64
Material control measures:
Purchase order lead time 10 days 9 days 7 days 5 days
Scrap as a percent of total cost 2 % 2 % 3 % 6 %
Machine performance measures:
Machine downtime as a percentage of availability 5 % 6 % 6 % 10 %
Use as a percentage of availability 95 % 92 % 89 % 85 %
Setup time (hours) 10 12 13 14
Delivery performance measures:
Throughput time ? ? ? ?
Manufacturing cycle efficiency (MCE) ? ? ? ?
Delivery cycle time ? ? ? ?
Percentage of on-time deliveries 96 % 95 % 92 % 89 %

The president has read in industry journals that throughput time, MCE, and delivery cycle time are important measures of performance, but no one is sure how they are computed. You have been asked to assist the company, and you have gathered the following data relating to these measures:

Average per Month (in days)
1 2 3 4
Wait time per order before start of production 10.0 12.9 13.0 15.0
Inspection time per unit 0.8 0.7 0.7 0.7
Process time per unit 2.8 2.1 2.0 1.0
Queue time per unit 3.1 4.9 5.9 7.6
Move time per unit 0.3 0.4 0.4 0.7

Required:

1-a. Compute the throughput time for each month.

1-b. Compute the manufacturing cycle efficiency (MCE) for each month.

1-c. Compute the delivery cycle time for each month.

3-a. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 5 the inspection time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate the queue time during production using Lean Production. Compute the new throughput time and MCE.

3-b. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 6 the inspection time, process time, and so forth, are the same as in month 4, except that the company is able to eliminate both the queue time during production and the inspection time using Lean Production. Compute the new throughput time and MCE.

image text in transcribedimage text in transcribed

Throughput Time Manufacturing Cycle Efficiency (MCE) Month 1 Month 2 Month 3 Month 4 days days days days Delivery Cycle Time days days days days % % Required 1 Required 3 > 3-a. (Month 5) Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 5 the inspection time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate the queue time during production using Lean Production. Compute the new throughput time and MCE. 3-b. (Month 6) Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 6 the inspection time, process time, and so forth, are the same as in month 4, except that the company is able to eliminate both the queue time during production and the inspection time using Lean Production. Compute the new throughput time and MCE. (Round your answers to 1 decimal place.) Show less Throughput time Manufacturing cycle efficiency (MCE) Month 5 days % Month 6 days % 3-a. (Month 5) Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 5 the inspection time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate the queue time during production using Lean Production. Compute the new throughput time and MCE. 3-b. (Month 6) Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 6 the inspection time, process time, and so forth, are the same as in month 4, except that the company is able to eliminate both the queue time during production and the inspection time using Lean Production. Compute the new throughput time and MCE. (Round your answers to 1 decimal place.) Show less Throughput time Manufacturing cycle efficiency (MCE) Month 5 days % Month 6 days %

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Markets And Institutions

Authors: Jeff Madura

10th Edition

1285531507, 9781285531502

More Books

Students also viewed these Finance questions