Question

1 Approved Answer

Total cost of crashing the project to minimum ( or maximum weeks possible ) = Activity Normal Time ( weeks ) Crash Time ( weeks

Total cost of crashing the project to minimum(or maximum weeks possible)= Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s)
A 43 $2,100 $2,700-
B 21 $2,100 $2,700-
C 33 $600 $600-
D 84 $2,500 $2,780 A
E 63 $800 $1,100 B
F 32 $3,200 $4,600 C
G 42 $1,600 $2,000 D, E

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

MIS Essentials

Authors: David M Kroenke

1st Edition

0136075606, 9780136075608

More Books

Students also viewed these General Management questions