"Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $2,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year Manufacturing overhead Direct labor Department Fabricating Machining $ 169,250 $ 422.000 $ 211,000 $ 195,500 Assembly $ 94,950 $ 316,500 Total Plant $ 886,200 $ 633,eee Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct labor Manufacturing overhead Fabricating $ 4,100 $ 5,00e Department Machining $4ee $700 Assembly $ 2.500 $2,300 Total Plant 57.000 $13,00 Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor and applied overhead). a What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 1B Required 2A Required 2B Required 4A Required 4B Compute the plantwide predetermined rate for the current year. Predetermined overhead rate % of direct labor cost Recuired 1A Required 1B > Complete this question by entering your answers in the tabs below. Required 1A Required 1B Required 2A Required 2B Required 4A Required 4B Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Manufacturing overhead cost applied complete this question by entering your answers in the tabs below. Required 1A Required 1B Required 2A Required 2B Required 4A Required 48 Compute the predetermined overhead rate for each department for the current year. Predetermined Overhead Rate Fabricating department % Machining department % Assembly department % of direct labor cost of direct labor cost of direct labor cost (Required 1B Required 2B > Complete this question by entering your answers in the tabs below. Required 1A Required 1B Required 2A Required 2B Required 4A Required 4B Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Manufacturing overhead cost applied Complete this question by entering your answers in the tabs below. Required 1A Required 1B Required 2A Required 2B Required 4A Required 4B What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? Company's bid price syusuun oy entering your answers in the tabs below. Required 1A Required 1B Required 2A Required 2B Required 4A Required 4B What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Manufacturing overhead cost applied