Consider the following two projects: Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount Project C/F C/F
Consider the following two projects: Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount Project C/F C/F C/F C/F C/F C/F C/F Rate Alpha - 79 20 25 30 35 40 NA N/A 16% Beta - 80 25 25 25 25 25 25 25 17% C/F The net present value (NPV) for project alpha is closest to: O A. $14 B. $12 O C. $22 OD. $18