Using the Three-Point Estimating and Beta Distribution, what is the Expected Activity Cost if: (1) Most Likely Duration is 111 hours, (2) Optimistic Duration is
Using the Three-Point Estimating and Beta Distribution, what is the Expected Activity Cost if: (1) Most Likely Duration is 111 hours, (2) Optimistic Duration is 80 hours, and (3) Pessimistic Duration is 130 Hours? Assume a labor rate of $83/Hr. O $15,582 O $8,881 $6,664 O $4,984