Question

1 Approved Answer

Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) 132.00 Direct labor (6 hrs.

Trico Company set the following standard unit costs for its single product.

Direct materials (30 Ibs. @ $4.40 per Ib.) 132.00
Direct labor (6 hrs. @ $14 per hr.) 84.00
Factory overheadVariable (6 hrs. @ $8 per hr.) 48.00
Factory overheadFixed (6 hrs. @ $11 per hr.) 66.00
Total standard cost 330.00

The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 50,000 units per quarter. The following flexible budget information is available.

Operating Levels
70% 80% 90%
Production in units 35,000 40,000 45,000
Standard direct labor hours 210,000 240,000 270,000
Budgeted overhead
Fixed factory overhead 2,640,000 2,640,000 2,640,000
Variable factory overhead 1,680,000 1,920,000 2,160,000

During the current quarter, the company operated at 90% of capacity and produced 45,000 units of product; actual direct labor totaled 266,000 hours. Units produced were assigned the following standard costs.

Direct materials (1,350,000 Ibs. @ $4.40 per Ib.) 5,940,000
Direct labor (270,000 hrs. @ $14 per hr.) 3,780,000
Factory overhead (270,000 hrs. @ $19 per hr.) 5,130,000
Total standard cost 14,850,000

Actual costs incurred during the current quarter follow.

Direct materials (1,333,000 Ibs. @ $6.20 per lb.) 8,264,600
Direct labor (266,000 hrs. @ $12.50 per hr.) 3,325,000
Fixed factory overhead costs 2,443,000
Variable factory overhead costs 2,287,000
Total actual costs 16,319,600

Problem 08-4A Computing materials, labor, and overhead variances LO P3, P4

Required: 1. Compute the direct materials cost variance, including its price and quantity variances. 2. Compute the direct labor cost variance, including its rate and efficiency variances. 3. Compute the overhead controllable and volume variances.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Commercial Energy Auditing Reference Handbook

Authors: Steve Doty

3rd Edition

1498769268, 978-1498769266

More Books

Students also viewed these Accounting questions