Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Turner's Furniture has developed a new style of chairs that will be made on an assembly line. The schedule requires 7 5 chairs in an
Turner's Furniture has developed a new style of chairs that will be made on an assembly line. The schedule requires chairs in an hour day. The assembly includes seven tasks. The table below indicates the performance time and the sequence requirements for each task.
Task
Performance Time minutes
Predecessor
A
B
A
C
B
D
B
E
C D
F
E
G
F
Based on utilizing the Longest Operating Time heuristic:
a What is the cycle time for this assembly operation?
Select
b What is the theoretical minimum number of workstations?
Select
c Where you able to balance the problem to achieve the theoretical number of stations?
Select
d Based on utilizing the longest operating time rule, what station should task D be assigned to
Select
Task F
Select
e Is there an opportunity to improve the line balance?
Select
If so what is the cycle time, idle time, and efficiency?
Select
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started