Turner's Furniture has developed a new style of chairs that will be made on an assembly line. The schedule requires 7 5 chairs in an

Turner's Furniture has developed a new style of chairs that will be made on an assembly line. The schedule requires 75 chairs in an 8-hour day. The assembly includes seven tasks. The table below indicates the performance time and the sequence requirements for each task.
Task
Performance Time (minutes)
Predecessor
A
1
B
2
A
C
3
B
D
2
B
E
4
C, D
F
1
E
G
2
F
Based on utilizing the Longest Operating Time heuristic:
a. What is the cycle time for this assembly operation?
[ Select ]
b. What is the theoretical minimum number of workstations?
[ Select ]
c. Where you able to balance the problem to achieve the theoretical number of stations?
[ Select ]
d. Based on utilizing the longest operating time rule, what station should task D be assigned to?
[ Select ]
Task F?
[ Select ]
e. Is there an opportunity to improve the line balance?
[ Select ]
. If so, what is the cycle time, idle time, and efficiency?
[ Select ]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

12th Edition

840062338, 840062346, 9780840062338, 978-0840062345

More Books

Students also viewed these General Management questions