Tutorial 4 : Resource Utilization An aircraft component manufacturing and assembly company utilizes mainly 4 types of aircraft structural components. The manufacturing shop comprises of

Tutorial 4: Resource Utilization
An aircraft component manufacturing and assembly company utilizes mainly 4 types of aircraft structural components. The manufacturing shop comprises of 6 work centres which are used to manufacture the components and there is an infinite supply of raw materials for these machines to produce the components. Assembly is done as per order, and it takes 12 min to complete. The objective is to find the status of resources in 8 hours shift and the utilization of resources. Also comment on optimization of the floor
The production material flow diagram is given below.
Once the parts are assembled a Forklift is used to transfer parts from the order assembly area with a processing time of 12 min to storage. The processing time of the machines is given below. The order arrival table for each orders is given below,
Machine Name
Processing Time
Order Number
Order Arrival Time
8:20
2
8:50
Machine 1A
7 min
E
8:55
Machine 18
9 min
9:20
Machine ZA
8 min
5
9:40
6
10:10
Machine IC
2 min
10:30
Machine 10
1 min
B
10:50
Machine 2D
6 min
11:40
10
12:10
11
13:20
12
13:50

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Mind Management Not Time Management

Authors: David Kadavy

1st Edition

0578733692, 978-0578733692

More Books

Students also viewed these General Management questions