Two days ago, a project team was tasked to prepare time and cost estimates for a fixed price 5-year road construction bid. Today they have

Two days ago, a project team was tasked to prepare time and cost estimates for a fixed price 5-year road construction bid. Today they have an estimate document ready to be presented to Management. 
Based on which approach (top down/bottom up) would you consider the estimation is done? 
What accuracy range should be considered for such an estimation? Explain in less than 2 lines.


Step by Step Solution

3.41 Rating (154 Votes )

There are 3 Steps involved in it

Step: 1

The estimation is most likely done using the topdown approach This is because the project team was g... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management The Managerial Process

Authors: Eric W Larson, Clifford F. Gray

8th Edition

1260570436, 978-1260570434

More Books

Students also viewed these General Management questions

Question

=+a) Find a linear model for this series.

Answered: 1 week ago

Question

How many types of bankruptcy and these types explained in Chapters?

Answered: 1 week ago

Question

Have you ever used bets to motivate someone? How effective was it?

Answered: 1 week ago

Question

What is the difference between managing and leading a project?

Answered: 1 week ago