Two members of a crew work on floor tiles in the kitchen. The total floor area is 62 SF. If the crew productivity is 8
Two members of a crew work on floor tiles in the kitchen. The total floor area is 62 SF. If the crew productivity is 8 SF/hour: 1) Calculate the hours required to complete the work. 2) Daily salary of a crew member is $180, calculate the cost of labors to complete the work (assume 8 hours/day)