Question
Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations:
Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations:
a. Materials purchased on account, $29,800. | |
b. Materials requisitioned and factory labor used: |
Job | Materials | Factory Labor |
---|---|---|
301 | $ 2,960 | $2,775 |
302 | 3,620 | 3,750 |
303 | 2,400 | 1,875 |
304 | 8,100 | 6,860 |
305 | 5,100 | 5,250 |
306 | 3,750 | 3,340 |
For general factory use | 1,080 | 4,100 |
c. Factory overhead costs incurred on account, $5,500. | |
d. Depreciation of machinery and equipment, $1,980. | |
e. The factory overhead rate is $54 per machine hour. Machine hours used: |
Job | Machine Hours |
301 | 25 |
302 | 36 |
303 | 30 |
304 | 72 |
305 | 40 |
306 | 25 |
Total | 228 |
f. Jobs completed: 301, 302, 303 and 305. | |
g. Jobs were shipped and customers were billed as follows: Job 301, $8,250; Job 302, $11,200; Job 303, $15,000. |
Required: | |||
1. | Journalize the entries to record the summarized operations. Record each item (items a-f) as an individual entry on January 31. Record item g as 2 entries. Refer to the Chart of Accounts for exact wording of account titles. | ||
2. | Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month. | ||
3. | Prepare a schedule of unfinished jobs to support the balance in the work in process account.* | ||
4. | Prepare a schedule of completed jobs on hand to support the balance in the finished goods account.*
|
Chart of Accounts
CHART OF ACCOUNTS | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Tybee Industries Inc. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
General Ledger | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
Amount Descriptions
Amount Descriptions | |
Job No. 301 | |
Job No. 302 | |
Job No. 303 | |
Job No. 304 | |
Job No. 305 | |
Job No. 306 |
Journal
1. Journalize the entries to record the summarized operations. Record each item (items a-f) as an individual entry on January 31. Record item g as 2 entries. Refer to the Chart of Accounts for exact wording of account titles.
PAGE 10
JOURNAL
ACCOUNTING EQUATION
DATE | DESCRIPTION | POST. REF. | DEBIT | CREDIT | ASSETS | LIABILITIES | EQUITY | |
---|---|---|---|---|---|---|---|---|
1 |
| |||||||
2 |
| |||||||
3 |
| |||||||
4 |
| |||||||
5 |
| |||||||
6 |
| |||||||
7 |
| |||||||
8 |
| |||||||
9 |
| |||||||
10 |
| |||||||
11 |
| |||||||
12 |
| |||||||
13 |
| |||||||
14 |
| |||||||
15 |
| |||||||
16 |
| |||||||
17 |
| |||||||
18 |
|
T Accounts
2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month.
Work in Process | |||
Bal. |
Finished Goods | |||
Bal. |
Schedule of Unfinished Jobs
3. Prepare a schedule of unfinished jobs to support the balance in the work in process account. Refer to the list of Amount Descriptions for the exact wording of the answer choices for text entries.
Tybee Industries Inc. |
Schedule of Unfinished Jobs |
1 | Job | Direct Materials | Direct Labor | Factory Overhead | Total |
2 | |||||
3 | |||||
4 | Balance of Work in Process, January 30 |
|
|
|
Schedule of Completed Jobs
4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account. Refer to the list of Amount Descriptions list for the exact wording of the answer choices for text entries.
Tybee Industries Inc. |
Schedule of Completed Jobs |
1 | Job | Direct Materials | Direct Labor | Factory Overhead | Total |
2 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started