Question

1 Approved Answer

Umanzor Corporation uses activity-based costing to assign overhead costs to products. Overhead costs have already been allocated to the company's three activity cost pools as

Umanzor Corporation uses activity-based costing to assign overhead costs to products. Overhead costs have already been allocated to the company's three activity cost pools as follows: Processing, $45,400; Supervising, $30,400; and Other, $17,400. Processing costs are assigned to products using machine-hours (MHs) and Supervising costs are assigned to products using the number of batches. The costs in the Other activity cost pool are not assigned to products. Activity data appear below:

MHs (Processing) Batches (supervising)
Product S5 12,600 900
Product F5 740 1,010
Total

13,340

1,910

The activity rate for the Processing activity cost pool under activity-based costing is closest to:

$3.70 per MH

$3.40 per MH

$3.08 per MH

$7.83 per MH

What is the overhead cost assigned to Product S5 under activity-based costing? (Round your intermediate calculations to 2 decimal places.)

$42,840.00

$41,700.00

$57,168.00

$14,328.00

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions