undefinednot precisely limited, determined, or distinguishedMore (Definitions, Synonyms, Translation) Use the activities whose sequence is described by the following table: Activity letter Immediate predecessor Activity
undefinednot precisely limited, determined, or distinguishedMore (Definitions, Synonyms, Translation) Use the activities whose sequence is described by the following table: Activity letter Immediate predecessor Activity Time 3 B 5 A,B 2 D 6 E 5 F E 3 4 H 3 I D, G, F D, F H 4 2 K 2 1. What is the slack time for activity D? 2. Which activities are on the critical path? 3. What is the project duration