Under the American Institute of Architects ( AIA ) A 2 0 1 - 2 0 1 7 General Conditions, what can a General Contractor

Under the American Institute of Architects (AIA) A201-2017 General Conditions, what can a General Contractor do if the Owner has repeatedly suspended, delayed, or interrupted its work for more than 120 days in a 365-day period?
Group of answer choices
Demobilize from the project without notice.
Request an award for punitive damages from the Initial Decision Maker (the Architect).
Terminate the contract with 7 days notice.
Nothing, so long as the suspensions by the Owner were allowed under the contract.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

An Introduction to Management Science Quantitative Approach to Decision Making

Authors: David R. Anderson, Dennis J. Sweeney, Thomas A. Williams, Jeffrey D. Camm, James J. Cochran

15th edition

978-1337406529

More Books

Students also viewed these General Management questions

Question

What are the four commonly cited philosophies of business ethics?

Answered: 1 week ago

Question

A. everyone who wants a college education should get one

Answered: 1 week ago