Under the American Institute of Architects ( AIA ) A 2 0 1 - 2 0 1 7 General Conditions, what can a General Contractor
Under the American Institute of Architects AIA A General Conditions, what can a General Contractor do if the Owner has repeatedly suspended, delayed, or interrupted its work for more than days in a day period?
Group of answer choices
Demobilize from the project without notice.
Request an award for punitive damages from the Initial Decision Maker the Architect
Terminate the contract with days notice.
Nothing, so long as the suspensions by the Owner were allowed under the contract.