URGENT HELP PLEASE - Following table provides tasks on an assembly line, along with their immediate predecessors and task times. Task Time (Minutes) Immed. Pred.

URGENT HELP PLEASE -

  1. Following table provides tasks on an assembly line, along with their immediate predecessors and task times.
Task Time (Minutes) Immed. Pred.
A 0.7 None
B 0.2 A
C 0.4 None
D 1.0 B
E 0.3 A
F 0.5 C
G 0.7 D,E,F
H 1.2 G

The cycle time is 1.3 minutes. Draw precedence diagram. Balance the line (assign all tasks) using the longest task time rule and fill out below table. Calculate the efficiency.

Following table provides tasks on an assembly line, along with their immediate predecessors and task times.

Task Time (Minutes) Immed. Pred.
A 0.7 None
B 0.2 A
C 0.4 None
D 1.0 B
E 0.3 A
F 0.5 C
G 0.7 D,E,F
H 1.2 G

The cycle time is 1.3 minutes. Draw precedence diagram. Balance the line (assign all tasks) using the longest task time rule and fill out below table. Calculate the efficiency.

Work station Eligible Task Task time Idle time

2. A decision tree is provided.

A. Calculate Expected value (EV) at every node. Show work.

B. What is the optimum decision and EV?

C. If your risk tolerance is $0, what is the best decision and EV?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Fundamentals

Authors: Robert N. Lussier

9th Edition

154438419X, 978-1544384191

More Books

Students also viewed these General Management questions