Use EVM to make the following calculations. 1. EV=225, PV=200, AC=255. What is CPI? What does this calculation tell you? 2. PV=11,000 AC=6,000 CV=4,000. What

Use EVM to make the following calculations.

image text in transcribed
1. EV=225, PV=200, AC=255. What is CPI? What does this calculation tell you? 2. PV=11,000 AC=6,000 CV=4,000. What is SV? What does this calculation tell you? 3. ETC= 220,000 PV = 25,000 AC=40,000. What is EAC? What does this calculation tell you? For questions 4-8, here are the project numbers: EV 10,500 AC 12,000 PV 13,000 BAC 15,000 4. Calculate CV? What does that tell you about the project? 5. Calculate SV? What does that tell you about the project? 6. Calculate SPI? What does that tell you about the project? 7. Calculate CPI? What does that tell you about the project? 8. Calculate EAC? What does that tell you about the project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management A Competitive Advantage Approach Concepts

Authors: Fred R. David, Forest R. David

15th edition

978-0133444896, 133444791, 9780133444858, 133444899, 133444856, 978-0133444797

More Books

Students also viewed these General Management questions

Question

11. How often are Client matters discussed at board level?

Answered: 1 week ago

Question

Thomas Aquinas was born........?

Answered: 1 week ago

Question

Aristotle of ideal state features?

Answered: 1 week ago