Question
use the Figure below shows a WBS with 11 tasks. Note that each task has an ID, a description, duration, and a reference to predecessor
use the Figure below shows a WBS with 11 tasks. Note that each task has an ID, a description, duration, and a reference to predecessor tasks, if any, which must be completed before the task can begin. Also note that dependent tasks can have one predecessor task or several. Construct a PERT/CPM chart from these tasks. Recall that this is done as a two-step process: (1) display the tasks and task patterns, and (2) enter start and finish time.
Please help me make a PERT Chart .may be created in any format you want but readable please. Make task boxes for each task that includes the task name, start and finish times, task ID and task duration. Please explain also What is the critical path and how long will it take, Specifically state both of these.
Task Description Duration | Predecessor No. [Days) Tasks Develop Plan 2 Assign Tasks 4 | 3 Obtain Hardware |7 | 4 Programming 70 2 5 Install Hardware 10 3 6 Program Test 30 4 7 Write User Manual 25 5 8 Convert Files 20 5 2 System Test 25 6 |10 User Training 20 7,8 | | User Test 25 9,10 q Example of a work breakdown structure listing | | tasks, together with their descriptions, durations, and predecessor tasksStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started