Use the following data for problems 5 and 6. Assume all the activities are on the critical path. Activity Optimistic Time Most Likely Time Pessimistic

Use the following data for problems 5 and 6. Assume all the activities are on the critical path.

Activity Optimistic Time Most Likely Time Pessimistic Time
A 2 8 12
B 1 5 20
C 12 14 16
D 8 25 27

5. The expected time for activity D is?

  1. 6.83
  2. 22.5
  3. 18.2
  4. 6.17

6. What is the variance for activity B?

  1. 8.12
  2. 3.02
  3. 10.03
  4. 2.78

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Calculus Early Transcendentals, Multivariable

Authors: Michael Sullivan, Kathleen Miranda

2nd Edition

131924288X, 9781319242886

More Books

Students also viewed these Mathematics questions

Question

2. Are my sources up to date?

Answered: 1 week ago