Question
1 Approved Answer
Use the following data to calculate the variences (price, effeciency, and flexible budget AKA TOTAL) for 1. Direct Materials 2. Direct Labor 3. Variable MOH
Use the following data to calculate the variences (price, effeciency, and flexible budget AKA TOTAL) for
1. Direct Materials
2. Direct Labor
3. Variable MOH variences
4. Fixed MOH variences
***note, OH is allocated based on DL hours
Standards (for a planned level of production of 2,100 units per month) | |||
Direct Materials: | |||
Yards per costume | 12.00 | yards | |
Price per yard | $26.50 | average | |
Direct Labor: | |||
D.L. Hours per costume | 60.00 | hours | |
D.L. Rate per hour | $45.00 | average | |
Variable MOH standard rate per direct labor hour | $4.85 | per D.L. hour | |
Fixed MOH standard rate per direct labor hour | $10.32 | per D.L. hour | |
Total Budgeted Fixed MOH (for 1 month) | $1,300,000 | ||
Actual cost and data from the current month: | |||
Actual number of yards of materials purchased | 28,000 | ||
Actual cost of materials purchased | $800,000 | $28.57 | per yd |
Actual number of yards used in production | 26,350 | ||
Actual number of costumes produced | 2,200 | ||
Actual direct labor hours | 134,500 | ||
Actual direct labor cost | $5,112,000 | $38.01 | per hr |
Actual variable MOH (in total) | $673,000 | ||
Actual fixed MOH (in total) | $1,458,000 | ||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started