Use the following data to find the direct labor efficiency variance. Direct labor standard (4.0 hrs.@ $ 7/hr.) $28per finished unit Actual hours worked per
Use the following data to find the direct labor efficiency variance. |
Direct labor standard (4.0 hrs.@ $ 7/hr.) | $28per finished unit |
Actual hours worked per unit | 3.5 hrs |
Actual units produced | 5,300 units |
Actual rate per hour | $7.25 |
rev: 11_05_2014_QC_58619
$4,638 unfavorable
$4,638 favorable
$18,550 favorable
$21,200 unfavorable
$21,200 favorable