Use the following information about a PERT project to answer Q38-39. Times are in days. Assume only one critical path exists which is: B, C,

Use the following information about a PERT project to answer Q38-39.

Times are in days. Assume only one critical path exists which is: B, C, E, F

Activity optimistic Most likely pessimistic Critical?
A 4 6 9 No
B 2 3 9 Yes
C 12 14 15 Yes
D 10 28 29 No
E 3 4 5 Yes
F 2 4 6 Yes

38. What is the expected project completion time?

a. 25.7 days

b. 30.0 days

c. 23.4 days

d. 57.0 days

39. What is the standard deviation of project completion time?

a. 1.47 days

b. 2.17 days

c. 1.06 days

d. 3.44 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Credit Portfolio Management

Authors: Arik Ben Do, Lev Dynkin, Jay Hyman, Bruce D. Phelps

1st Edition

1118117697, 978-1118117699

More Books

Students also viewed these General Management questions

Question

Describe the major barriers to the use of positive reinforcement.

Answered: 1 week ago