Use the following information to answer questions 18 - 21 The budgeted and actual costs at Goodyear Company (a tire manufacturer) are as follows: Budgeted

Use the following information to answer questions 18 - 21

The budgeted and actual costs at Goodyear Company (a tire manufacturer) are as follows:

Budgeted costs

Materials (per tire) 12 lbs @ $1.80/lb

Labor (per tire) 4 hrs. @ $14/hr

Factory O/H (per tire) 3 hrs. @ $8/hr

Actual costs

Total materials purchased 840,000lbs

Total cost of purchase $1,554,000

Total material used 849,600 lbs

Labor (per tire) 4.1 hrs @ $13/hr

Factory O/H (per tire) 2.8 hrs @ $8.50/hr

During October, Goodyear produced 72,000 tires.

Determine the budgeted & actual cost, respectively, of producing one tire? (round to the nearest $)

Question 18 options:

a)

$102 and $99

b)

$78 and $98

c)

$102 and $98

d)

$102 and $95

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Explain the forces that influence how people handle conflict

Answered: 1 week ago