Use the following information to answer questions 18 - 21 The budgeted and actual costs at Goodyear Company (a tire manufacturer) are as follows: Budgeted
Use the following information to answer questions 18 - 21
The budgeted and actual costs at Goodyear Company (a tire manufacturer) are as follows:
Budgeted costs
Materials (per tire) 12 lbs @ $1.80/lb
Labor (per tire) 4 hrs. @ $14/hr
Factory O/H (per tire) 3 hrs. @ $8/hr
Actual costs
Total materials purchased 840,000lbs
Total cost of purchase $1,554,000
Total material used 849,600 lbs
Labor (per tire) 4.1 hrs @ $13/hr
Factory O/H (per tire) 2.8 hrs @ $8.50/hr
During October, Goodyear produced 72,000 tires.
Determine the budgeted & actual cost, respectively, of producing one tire? (round to the nearest $)
| |||
| |||
| |||
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started