USE THE FOLLOWING INFORMATION TO ANSWER THE QUESTIONS: During Year 1, Sparky Construction Company has a contract to construct a $4,500,000 high-rise apartment building at
USE THE FOLLOWING INFORMATION TO ANSWER THE QUESTIONS:
During Year 1, Sparky Construction Company has a contract to construct a $4,500,000 high-rise apartment building at an estimated cost of $4,000,000. The contract is to start in July of Year 1 and the high-rise apartment building is to be completed in October of Year 3. The following data pertain to the construction period (Note: by the end of Year 2, Sparky has revised the estimated total cost from $4,000,000 to $4,050,000)
Year 1 | Year 2 | Year 3 | |
Costs to Date | $1,000,000 | $2,916,000 | $4,050,000 |
Estimated costs to complete | $3,000,000 | $1,134,000 | $ - 0 - |
Progress billings during the year | $ 900,000 | $2,400,000 | $1,200,000 |
Cash collected during the year | $ 750,000 | $1,750,000 | $2,000,000 |
determine how much Revenue Sparky should report in Year 3. $________________________
Using the information above, determine the amount of Gross Profit Sparky should report in Year 2: $______________________________
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started