Use the following information to compute the number of kanbans (trays) necessary for this process: Average leadtime = 4.0 hours Average demand during leadtime =
Use the following information to compute the number of kanbans (trays) necessary for this process:
Average leadtime = 4.0 hours Average demand during leadtime = 95 parts per hour Safety stock needed = 10% Each tray or kanban holds 80 parts
The calculated value for the number of kanbans or trays needed for this process is:
A. 380 trays
B. 6 trays
C. 5 trays
D. 5.225 trays
E. 418 trays
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To calculate the number of kanbans trays necessary for the process we use the formula n fracD times ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started