Use the following project information. Construct a network diagram using AON notation. Activity Activity Time (weeks) Immediate Predecessor(s) A 3 none B 4 A C
Use the following project information. Construct a network diagram using AON notation.
Activity | Activity Time (weeks) | Immediate Predecessor(s) |
A | 3 | none |
B | 4 | A |
C | 2 | B |
D | 5 | B |
E | 4 | C |
F | 3 | D |
G | 2 | E,F |