Question
Use the following table to calculate duration (round to 0 decimal places) ID TASK NAME Optimistic Most likely Pessimistic Precedence Duration 1 First 1 2
Use the following table to calculate duration (round to 0 decimal places)
ID | TASK NAME | Optimistic | Most likely | Pessimistic | Precedence | Duration |
1 | First | 1 | 2 | 4 |
|
|
2 | Second | 3 | 5 | 10 | 1 |
|
3 | Third | 9 | 11 | 13 | 2 |
|
4 | Fourth | 3 | 5 | 6 | 3,8,9 |
|
5 | Fifth | 6 | 7 | 8 | 4,11 |
|
6 | Sixth | 5 | 6 | 8 | 1 |
|
7 | Seventh | 3 | 5 | 8 | 6 |
|
8 | Eighth | 1 | 2 | 5 | 7 |
|
9 | Ninth | 1 | 3 | 5 | 6 |
|
10 | Tenth | 4 | 5 | 6 | 9,8 |
|
11 | Eleventh | 3 | 4 | 5 | 10 |
|
12 | Twelfth | 4 | 5 | 6 | 11 |
|
13 | Done | 0 | 0 | 0 | 5,12 |
|
Use Activity on Node to construct a network activity diagram with the preceding table.
ES | Task | LS |
EF | Dur | LF |
Use the forward and backward pass method to calculate project duration. Include slack on the arrows and identify the critical path(s) and burst and merge activities.
Evaluate the finished project and write a review of your analysis and how you completed each step. Include the completed table and your AON diagram in your paper
Your response should be integrated in a well-written paper that meets the following requirements:
- Be 2-3 pages in length plus graphical elements, placing these graphical elements in an appendix,
- Be formatted according to the APA Style
- Include two scholarly sources
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started