Use the given priority list to schedule the project described by the project digraph shown in Fig. 4 using N = 2 processors. Show the
Use the given priority list to schedule the project described by the project digraph shown in Fig. using processors. Show the timeline for the project, and give the project finishing time.
Fig.
Priority list: