Use the information below, find out the probability of completing the project within 28 days. Assuming that A-B-C-D collectively is a critical path. Also, what
- Use the information below, find out the probability of completing the project within 28 days. Assuming that A-B-C-D collectively is a critical path. Also, what duration will give a 98% confidence in terms of duration estimation?
Event | Pessimistic | Most Likely | Optimistic |
A | 22 | 12 | 2 |
B | 16 | 7 | 4 |
C | 9 | 6 | 5 |
D | 6 | 3 | 1 |