Question

1 Approved Answer

Use the information below, find out the probability of completing the project within 28 days. Assuming that A-B-C-D collectively is a critical path. Also, what

  1. Use the information below, find out the probability of completing the project within 28 days. Assuming that A-B-C-D collectively is a critical path. Also, what duration will give a 98% confidence in terms of duration estimation?

Event Pessimistic Most Likely Optimistic
A 22 12 2
B 16 7 4
C 9 6 5
D 6 3 1

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Creating Value Along the Supply Chain

Authors: Roberta S. Russell, Bernard W. Taylor

7th Edition

9781118139523, 0470525908, 1118139526, 978-0470525906

More Books

Students also viewed these General Management questions