Use the information below (WBS code, activity, predecessors and duration) to create a two pass AoN, including the ES, EF, LS, LF, Float and critical

Use the information below (WBS code, activity, predecessors and duration) to create a two pass AoN, including the ES, EF, LS, LF, Float and critical path, then use the other information provided below to crash your project and provide an updated AoN (including resources) to optimize your project.

Initially there was a limitation to one person doing one task at a time to improve time you can have both apprentices can work together, contractor and son can work together and Apprentice II can assist the project manager

It is up to you how many activities you crash, none, all, or any number in between.

The only task that cannot be crashed is the shopping on day 1

image text in transcribedimage text in transcribed
Documenll Home Insert Design Layout References Mailings v X Calibri(Body) v 11 leA Av an Al SEVEE'HE' E E Q; 1] Pastev BIQVabexzx2 A'Q'Av' No spacing Heading 1 Heading 2 Title Subtitle Styles _ Pane AaBbCEDdEe AaEbCEDdEe AaBchD

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Process

Authors: Lee Long

4th Edition

978-0201822939,0201822938

More Books

Students also viewed these General Management questions

Question

Find the unit vector in the opposite direction of (1,2,3)

Answered: 1 week ago