Question
Use the information contained below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point
Use the information contained below to compress one-time unit per move using the least cost
method. Reduce the schedule until you reach the crash point of the network. For each move identify
what activity(ies) was crashed and the adjusted total cost.
Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost 120 2 4 200+240 100 2 4 150+200 90 3 140+180 30 1 2 70+30 50 4 80+100 120+120 180+80 60 3 40 4 20 1 2 130+20 2040 Project duration 9 1xx 3xx B 2xx H A G 1 2xx Total direct cost 2040 E. ABCDDEFGH
Step by Step Solution
3.51 Rating (144 Votes )
There are 3 Steps involved in it
Step: 1
Summary Step Duration ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Project management the managerial process
Authors: Eric W Larson, Clifford F. Gray
5th edition
73403342, 978-0073403342
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App