Use the project activities that follow to determine the following: (a) Construct a Gantt chart; indicate the project completion time and slack for each activity.
Use the project activities that follow to determine the following:
(a) Construct a Gantt chart; indicate the project completion time and slack for each activity.
(b) Construct the CPM/PERT network, compute the length of each path in the network, and indicate the critical path.
ACTIVITY | ACTIVITY PROCESSOR | TIME (WEEKS) |
1 | - | 4 |
2 | - | 7 |
3 | 1 | 8 |
4 | 1 | 3 |
5 | 2 | 9 |
6 | 3 | 5 |
7 | 3 | 2 |
8 | 4,5,6 | 6 |
9 | 2 | 5 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started