Question
Use this information to complete this question: Crash the above project to the maximum days it can be crashed at the least cost. For each
Use this information to complete this question: Crash the above project to the maximum days it can be crashed at the least cost. For each stage (day) that the project is crashed, fill out the following table. If more rows are needed, please add them manually.
Stage | Critical path/s | Total project time before crashing | Crash activity/ies | Crash cost added | Total crash cost of the project | Total project time after crashing |
1 |
|
|
|
|
|
|
2 |
|
|
|
|
|
|
3 |
|
|
|
|
|
|
What happens to the slack time of activity B if the duration of activity C reduced by 2 days? Explain your answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started