Question
Use WBS activity costs provided below to calculate total project cost. Project overhead is 20% of total WBS activity cost. Show cost with and without
Use WBS activity costs provided below to calculate total project cost. Project overhead is 20% of total WBS activity cost. Show cost with and without overhead costs.
Activity Cost | |
WBS Item | |
R&D Project Development | |
Need Survey | $ 64,000 |
Set Product Specs | $ 57,600 |
Shelf life Report | $ 19,200 |
Nutrition Report | $ 9,600 |
Select Fruit Suppliers | $ 9,600 |
Initial Production | |
Equipment Rehab | $ 528,000 |
Production Trials | $ 235,200 |
Quality Trials | $ 125,000 |
Quality Metrics | $ 17,000 |
Quality Training | $ 200,000 |
Distribution | |
Market Testing | $ 96,000 |
Package Design | $ 31,200 |
Select Distributors | $ 80,000 |
Legal | |
Complete FDA Certification | $ 60,000 |
Register Trademark | $ 14,400 |
Prepare Product Launch | $ 268,800 |
Overhead = 20% total cost of WBS activities |
Using your WBS Outline, AON, and the rules listed on page 640 in the book, create a schedule (use dates) in Excel with the below column headings. Also, under Part 1 on page 640, use the listed rules in items 2,3,4,5, and 6 to identify the dates. Ignore items 1 and 7. Each row/activity should have the below columns completed
WBS Task ID Task Name Start Date Finish Date Late Start Date Late Finish Date Slack Days total
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started