Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for Budgeted Output Pizza Vesuvio makes specialty pizzas. Data for the past 8 months
Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for Budgeted Output
Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected:
Month | Labor Cost | Employee Hours | |||
January | $7,200 | 340 | |||
February | $10,099 | 530 | |||
March | $8,340 | 610 | |||
April | $9,987 | 590 | |||
May | $8,690 | 460 | |||
June | $7,731 | 330 | |||
July | $9,690 | 550 | |||
August | $7,650 | 290 |
Assume that this information was used to construct the following formula for monthly labor cost.
Total Labor Cost = $7024 + ($2.16 x Employee Hours) |
Required:
Assume that 695 employee hours are budgeted for the month of September. Use the total labor cost formula for the following calculations:
1. Calculate total variable labor cost for September. Round your answer to nearest whole number. $fill in the blank 1
2. Calculate total labor cost for September. Round your answer to nearest whole number. $fill in the blank 2
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started