Question
1 Approved Answer
Using Taylors Differential Piece Rate System, calculate the earnings of workers from the following information: Normal rate per hour = 12 OMR Standard time per
Using Taylors Differential Piece Rate System, calculate the earnings of workers from the following information:
Normal rate per hour = 12 OMR
Standard time per piece = 20 minutes
Differentials to be applied.
- 83% of Piece rate below standard.
- 120% of Piece rate at or above standard.
In a 9-hour day, Labor A produces 26 units and Labor B produces 30 units.